Sirjan VI 132/20 & Extension of Sirjan II 400/132 & Extension of Kerman Industrial Own 132/20 High Voltage Substations

Kerman Regional Electric Co.

Additional Info

  • Subject: EPC Of Sirjan VI 132/20 & Extension of Sirjan II 400/132 & Extension of Kerman Industrial Own 132/20 High Voltage Substations
  • State: FAC
  • Province: Kerman
  • Client: Kerman Regional Electric CO
  • Consultant: Ghods Niroo
  • Start Date: 2004/09 /21
  • Guarantee Period: 12 Months
  • Amount of Contract: 19،821،938،160 Rials
  • Amend: 0
  • Percentage of Progress: 100
  • Duration of Contract: 18 Months